New 132/33kV power substation, Awendo
Civil works for a new 132/33kV substation in Migori County.
A new-build substation delivered from a green site: bulk earthworks, foundations across the yard, buildings, and the drainage and roads that finish the job.
Scope delivered
- Bulk earthworks and formation
- Transformer plinths and equipment foundations
- Oil pits, cable trenches and ducting
- Control building and ancillary structures
- Perimeter wall, drainage and roads
Keep looking
More projects
01
New 132/33kV power substation, Kitale
Full civil works scope for a new 132/33kV substation: formation, foundations, oil pits, trenches, control building, walls, drainage…
- Client
- Kenya Electricity Transmission Company (KETRACO)
- County
- Trans Nzoia
- Scope
- Civil works
02
132kV takeoff extension bay, Eldoret Rivertex substation
Civil works for a 132kV takeoff extension bay inside an operating substation.
- Client
- Kenya Electricity Transmission Company (KETRACO)
- County
- Uasin Gishu
- Scope
- Civil works
03
132kV takeoff extension bay, Kegati substation
Extension bay civil works on a sloping, high-rainfall site in Kisii.
- Client
- Kenya Electricity Transmission Company (KETRACO)
- County
- Kisii
- Scope
- Civil works